Opening a franchise unit: agree the approval criteria
When is a new franchise unit ready for customers? Agree the opening approval criteria, evidence of readiness and approach to delays before expanding.
Published

When turning your existing business into a franchise network, the opening date of your first franchisee-operated unit must not be driven by the calendar alone. A signed agreement, fitted-out premises and an enthusiastic franchisee do not yet prove that you can deliver the promised service to customers. You need an agreed process for approving the opening: what will be checked, who will sign off readiness and what happens if something essential is missing.
1. Separate the target date from permission to start trading
At your own premises, you may have personally resolved the final problems before opening. In a franchise network, this informal decision-making needs to be replaced with an agreed procedure. The franchisee must know the criteria for opening a unit under the shared brand.
When planning, distinguish between three things: the target opening date, the contractual obligation to open and the network’s internal readiness approval. They are not the same thing. Readiness approval does not replace any regulatory authorisation or the franchisee’s own statutory obligations either.
Set out the main approval principles in the franchise agreement. The practical checklist can be a separate working tool, but it should not be used to introduce significant new obligations after the agreement has been signed. The franchisee must be able to assess how the requirements will affect timings and costs before committing.
Appoint a person on each side to take responsibility for the opening. Also agree who can make the final decision and who will resolve any disagreement over readiness. This ensures that opening does not depend on who happens to answer the phone at the last minute.
2. Define acceptable evidence of readiness
A good opening checklist does more than ask whether something has been done. It specifies the evidence needed to confirm readiness. Otherwise, the same tick in a box could mean equipment has been ordered to one person, but installed and tested to another.
Focus the checklist on what matters for customer service and business continuity. A practical structure is:
- Customer service: the entire customer transaction or service experience has been tested from start to finish.
- Staff capability: the opening shift is staffed by people trained for their roles, with suitable cover arrangements in place.
- Systems: booking, ordering, payment and other functions essential to the franchise concept have been tested.
- Operational capacity: the products, equipment and supplies needed for opening are available.
- Customer communications: opening hours, contact details and service availability reflect the actual situation.
- Disruptions: the franchisee knows what to do during an interruption and where to get help.
For each item, record the person responsible, the deadline and the verification method. Evidence might include the result of a test transaction, confirmation that a delivery has been received or a training record. Do not collect documents simply as a precaution: retain what is genuinely needed to support the decision.
Build the checklist around the actual workflows in your existing business. Review which seemingly minor shortcomings have previously prevented sales or led to a poor customer experience. Turn those findings into clear checks.
3. Test the customer journey before opening to the public
A pre-opening rehearsal is neither a pilot of the franchise concept nor another training programme. Its purpose is to confirm that this particular unit’s people, premises, equipment and systems work together.
Arrange a controlled run-through covering a typical customer interaction and a few exceptions relevant to the concept. A service business might test booking, arrival, service delivery, payment and cancellation. In a shop, the equivalent process might run from receiving goods through to a purchase and handling a return.
Agree in advance whether to use test environments within the systems or live transactions. If real customers, payments or personal data are involved, the usual obligations apply. A rehearsal is no excuse for disregarding safety, data protection or consumer rights.
Record any shortcoming precisely: which stage failed, what needs to be corrected and how the correction will be checked. A vague assessment such as “the system does not work” is no help in making a decision. A clearly defined finding also helps distinguish a local problem from something that needs improving across the network.
4. Agree how to handle shortcomings and delays
Not every unfinished task requires the opening to be postponed. A missing decorative item is different from a payment system that does not work or a safety issue. Classify findings as either shortcomings that prevent opening or corrections that can be completed within an agreed period after opening.
Use conditional approval only where trading can begin lawfully and the promise made to customers can be fulfilled. Record the outstanding issue, the temporary procedure, who will fix it and the deadline. Do not accept a vague promise to deal with it later.
Finland has no dedicated franchising law, no specific statutory franchise pre-contractual disclosure procedure and no dedicated register of franchisors. Franchise relationships are governed by legislation including the Finnish Contracts Act and general principles of contract law. The Finnish Act on the Regulation of Contract Terms between Businesses and competition law may also apply. The Finnish Franchising Association’s Code of Ethics is a form of self-regulation, not legislation.
Have a lawyer review the terms, particularly those covering postponement, periods allowed for corrective action and responsibility for costs. Agree how to handle costs such as rent, replacement launch marketing and additional induction training. When assessing responsibility, distinguish between a shortcoming on the franchisee’s part, delayed performance by the franchisor and an obstacle caused by an external factor.
5. Document the decision and arrange the first review
Prepare a brief written summary of the opening decision. Record the unit assessed, the decision date, those giving approval, the checklist used and any outstanding corrective actions. Give both parties the same summary.
Arrange the first follow-up discussion at the same time. Alongside outstanding corrections, review whether actual customer volumes are in line with operational plans and whether support is available for day-to-day problems. Approval to open does not transfer the franchisee’s business risk to the franchisor or release either party from its own obligations.
Practical checklist: define the approval criteria before either party commits, require concrete evidence of readiness and document the decision. Announce a firm opening date only once there is sufficient confidence that the essential requirements will be met.
Sources
- Franchising-oppaat ja resurssit Suomi
- Mitä franchising-yrittäjyys on? | Holvipedia
- Mitä franchising-yrittäjyys on? | Holvipedia
- Franchising - Työ, työttömyys ja talous - Suomi.fi
- Franchising - Work, unemployment and finances - Suomi.fi
- Franchising - Starting a business
- Franchising - Grunda ett företag
- Franchising - Yrityksen perustaminen